TL;DR
- A construction estimate that wins and protects the margin prices every line at cost divided by 0.66: 24% overhead and a 10% profit goal.
- A carpenter's $31.55 mean wage becomes a $70 billable hour and a $106.06 sell rate.
- The sample job, a 5 x 8 bathroom remodel in Minneapolis with subcontracted plumbing and electrical, totals $18,257.55.
- The editable Excel workbook and the print-ready PDF are free. The full sample is also in a table below.
- Skip adding 34% to cost. On the sample job that nets $216 instead of $1,776.
- Price allowances and alternates as their own lines. Homeowner remodel cost searches peaked in March, at 1.96 times September.
A construction estimate template that wins the job writes the scope out by trade, prices every line at cost divided by 0.66 and lists the allowances, exclusions and payment draws. On our sample job, a 5 x 8 bathroom remodel in Minneapolis, the estimate totals $18,257.55.
This guide is for the owner or office manager of a small general contracting or remodeling company who writes the estimates. Every figure was read at its source on November 25, 2026.
Download this construction estimate template. The editable Excel workbook with the totals wired up, a field guide tab, and a print-ready PDF are free in the contractor templates pack, alongside the other trades.
What a construction estimate template holds: the sample job
The sample is a fictional company, Larchmont Builders, quoting a fictional homeowner in south Minneapolis. Her 1948 hall bath gets gutted and rebuilt on the same layout, with a licensed plumber and electrician as subcontractors.
Here is every line, with the same quantities, rates and totals as the workbook.
| Description | Qty | Unit | Rate | Amount |
|---|---|---|---|---|
| Demolition and protection | ||||
| Protect floors; remove tub, tile, vanity, toilet and drywall to studs | 12 | hr | $106.06 | $1,272.72 |
| Dumpster, 10 yard, 1 week, delivered and hauled away | 1 | each | $575.76 | $575.76 |
| Framing and rough carpentry | ||||
| Blocking for vanity, grab bar and niche; shim walls flat | 6 | hr | $106.06 | $636.36 |
| Lumber, fasteners and adhesive | 1 | lot | $227.27 | $227.27 |
| Plumbing (licensed subcontractor, our markup included) | ||||
| Rough-in and finish: tub drain and valve, vanity and toilet supply | 1 | each | $3,181.82 | $3,181.82 |
| Electrical (licensed subcontractor, our markup included) | ||||
| GFCI circuit, exhaust fan, vanity light and switching | 1 | each | $1,181.82 | $1,181.82 |
| Tile | ||||
| Backer board, waterproofing, set floor and tub walls (110 sq ft) | 13 | hr | $106.06 | $1,378.78 |
| Backer board, membrane, thinset and grout | 1 | lot | $530.30 | $530.30 |
| Drywall, paint and finishes | ||||
| Moisture-resistant drywall: hang, tape and finish, 3 trips | 8 | hr | $106.06 | $848.48 |
| Prime and paint walls, ceiling, door and trim | 6 | hr | $106.06 | $636.36 |
| Set vanity, toilet, mirror and accessories; trim and caulk | 8 | hr | $106.06 | $848.48 |
| Drywall, mud, tape, primer and paint | 1 | lot | $378.79 | $378.79 |
| Toilet, two-piece elongated, standard height | 1 | each | $303.03 | $303.03 |
| Allowances (customer picks; our cost shown, markup included in the rate) | ||||
| Vanity with top, sink and faucet ($1,500 at our cost) | 1 | allow | $2,272.73 | $2,272.73 |
| Tub, valve trim and shower head ($1,200 at our cost) | 1 | allow | $1,818.18 | $1,818.18 |
| Tile, 110 sq ft at $3 our cost | 1 | allow | $500.00 | $500.00 |
| Alternates (put 1 in the qty of each one accepted) | ||||
| Alt 1: tile upgrade to $10 a sq ft our cost | 1 | each | $1,166.67 | $1,166.67 |
| Alt 2: comfort-height toilet in place of the standard one | each | $606.06 | ||
| Permit and inspection (passed through at cost) | ||||
| City of Minneapolis building permit (sample fee) | 1 | each | $500.00 | $500.00 |
| Subtotal | $18,257.55 | |||
| Sales tax (0%) | $0.00 | |||
| ESTIMATE TOTAL | $18,257.55 | |||
The crew lines bill at $106.06 an hour. Every other line except the permit carries the same markup, allowances included. The permit passes through at cost.
The blank quantity on the comfort-height toilet keeps a declined alternate out of the total. The workbook adds only lines with both a quantity and a rate.

Walk the construction estimate template top to bottom
The ranking template pages hand over a grid. Procore's guide, for one, lists overhead and profit as sections and prints no figure for either. Here is what goes in each section, in the order it prints.
Identity, license and lead-safe certification
Business name, phone, license number and insurance. In Minnesota, the Department of Labor and Industry requires a residential building contractor or remodeler license to contract directly with a homeowner for more than one special skill. The sample spans carpentry, drywall and interior finishing, three of the eight in statute 326B.802.

Add your EPA lead-safe firm number. The EPA says anyone paid to disturb paint in housing built before 1978 must be certified, sole proprietors included. The sample house was built in 1948.
Estimate number, date and validity
Use a sequential number and a valid-until date. Jobber's quoting guide says most service businesses expire quotes after 30 days, and 14 to 21 days where material costs move fast. The sample prints 30 days and a date.
Customer and project address
Print both when they differ, plus the room, its size and the year the house was built.
Scope by trade division
Write one line per trade in the order the work happens:
- Demolition to studs and floor protection
- Framing: blocking for the vanity, grab bar and niche
- Plumbing and electrical, by licensed subcontractors
- Backer board, waterproofing and tile
- Moisture-resistant drywall and paint
- Finishes: vanity, toilet, mirror, accessories and trim
Then say what stays the same. "Same layout: no walls, drains or windows move" heads off the request to shift the toilet a foot.
Existing conditions
Write down what you checked and what you could not see. Rot found behind the tile then becomes a change order the customer was warned about in writing.
Allowances for finishes not yet picked
An allowance is a dollar amount held for something the customer has not chosen. The sample carries three at its cost: $1,500 for the vanity with top, $1,200 for the tub and valve trim and tile at $3 a square foot.
Give each one a date the picks are due and say how the difference is settled. The sample marks allowances up like any material, credits money left over and puts overages on a change order.
Passing allowances through at cost looks generous and costs you. Overhead is a share of every revenue dollar, so billing the sample's $3,800 of allowances and alternate at cost would cut its profit from $1,776 to about $288.
Subcontractors: markup shown or rolled in
Two ways to print a sub, and both give the same price. Rolled in, the plumbing is one line at $3,181.82. Shown, it is the plumber's $2,100 bid plus a $1,081.82 line for coordination and markup.
Rolled in reads cleaner. Shown suits a cost-plus job or a customer who asks. The sample rolls it in and says so in the section heading.
Permit and inspection
Say who pulls each permit, who meets the inspector and what the fee is. The City of Minneapolis bases building permit fees on the job's value, labor and materials included. The sample's $500 is a placeholder from Fixr's "about $500" for a bathroom. Enter your city's real fee and pass it through at cost.
Dumpster, protection and cleanup
Name the container, where it sits and for how long. Fixr puts a 10-yard dumpster at about $380 a week, which the sample marks up like any other cost. Add floor protection and daily cleanup.
Schedule and payment draws
Give a start week and the time on site. Nearly two-thirds of homeowners surveyed by This Old House said their bathroom remodel took one to four weeks. The sample says about three, and that the bathroom is out of use the whole time.
Draws are payments tied to finished stages. The sample asks for 10% at signing, 40% when the rough-in inspections pass, 40% when tile is grouted and 10% at the walkthrough.
Exclusions
List what the price does not cover. The sample leaves out moving walls or drains, heating changes, rot or mold work beyond what is listed and anything outside the bathroom.
Alternates
An alternate is a priced change the customer can accept or decline. The sample offers a tile upgrade, which this customer took, and a comfort-height toilet, which she declined. More on pricing them below.
Tax, terms and signature
The sample tax rate is 0% for a reason. The Minnesota Department of Revenue says contractors pay sales and use tax on the materials they buy and do not charge sales tax on construction contracts. Other states tax remodeling differently, so check yours.
Close with validity, the draws, exclusions, a change-order sentence, a warranty term and a signature line that records the alternates accepted.
Price each line from a $70 billable hour
Price equals direct cost divided by one minus overhead and profit. Direct cost is the labor, materials and subcontract work that go into this job and no other.
The labor line: a $31.55 wage becomes a $106.06 sell rate
The Bureau of Labor Statistics (BLS) puts the mean carpenter wage at $31.55 an hour in May 2025. Here is how that climbs to the rate on the estimate:
| Step | Figure | Source |
|---|---|---|
| Mean carpenter wage | $31.55 an hour | BLS, May 2025 |
| Times 1.45 for benefits and taxes | $45.75 | BLS employer costs, June 2026 |
| Divided by a 65% billable share | $70.38 | Field Promax, 300 HVAC companies |
| Rounded cost of a billable hour | $70 | Our sample |
| Divided by 0.66 | $106.06, the sell rate on the estimate | |
Unrounded, $70.38 divided by 0.66 is $106.64. The sample rounds to $70 to keep the lines easy to check by hand.
The 1.45 is the BLS employer cost row for construction, extraction, farming, fishing and forestry occupations: $46.65 of total compensation on $32.17 of wages in June 2026.
The billable share, the part of a paid hour a customer pays for, is the weak link. The only measured figure we found is HVAC: Field Promax tracked techs billing 5.7 of 8.8 paid hours, as ACHR News reported in June. Time your own crew.
Overhead and profit set the divisor
Overhead is every cost not tied to one job. NAHB's Remodelers' Cost of Doing Business study, reported in April, put operating expenses at 23.6% of revenue for fiscal 2024, owner's pay included.
The same study put average net profit at 6.3%. The sample rounds overhead to 24% and sets a 10% profit goal, which leaves 0.66 of each dollar for direct cost.
is the average markup on cost implied by NAHB's fiscal 2024 figures. Remodelers' cost of sales was 70.1% of revenue, and 1 divided by 0.701 is 1.427. The sample's 0.66 divisor is a 51.5% markup.
That is our arithmetic on NAHB's shares. The Journal of Light Construction made the same point in 2005: a 50% markup leaves a 33% gross margin.
What to add to a subcontractor's bid
We found no published figure for the markup on sub work alone, so set your own. The sample runs subs through the same 0.66 divisor, for two reasons.
NAHB counts trade contractor costs inside cost of sales, at 30% of revenue in 2024. So the average remodeler's 23.6% overhead is paid partly out of sub work. And the 2005 Journal of Light Construction piece says remodelers historically marked everything up the same.
A lower sub markup is a choice to earn less on that line. Buildertrend cites its 2023 industry report: over 30% of builders mark up projects by 25% or more.
The sample job, line by line
The crew hours, both sub bids and the supply lots are placeholders. No published figure gives them for a full bath, so use your own.
- Crew labor. 53 hours at $70 is $3,710 of cost. At $106.06 an hour it bills $5,621.18.
- Materials, subs and dumpster. $4,210 of cost bills $6,378.79.
- Allowances and the alternate. $3,800 of cost bills $5,757.58.
- The permit. $500 at cost brings the subtotal to $18,257.55.
Two checks keep the placeholder hours honest. Demolition bills $1,272.72, inside the $600 to $2,300 Fixr prints for demolition billed on its own.
Tile bills $12.53 a square foot, inside Fixr's $8 to $14 installer range.
Set your own numbers in the calculator below. Its default is the sample job.
The calculator's $17,758 is the estimate's $18,257.55 less the $500 permit, which passes through at cost.
Why adding your percentages to cost loses money
The common slip is adding overhead and profit to cost as one markup. On the sample, 34% on cost quotes $15,705. Overhead takes $3,769 of it, which leaves $216 of profit.
Markup is a share of cost, and overhead and profit are shares of the price. Dividing handles that. Our markup vs margin guide has the full conversion table.
Estimates priced right, but not enough of them going out?
Skill Mammoth builds websites and runs marketing for contractors and home service businesses. Start with an audit of the site that should be booking your estimate appointments.
Allowances and alternates are separate lines with separate prices
Allowances cover what the customer has not picked. Alternates price the upgrades. Each gets its own line, so the customer sees the base price and each choice on top of it.
| Choice | Line price | Estimate total |
|---|---|---|
| Base, tile at $3 a sq ft | Included | $17,090.88 |
| Alt 1: tile at $10 a sq ft | $1,166.67 | $18,257.55 |
| Alt 1 plus Alt 2: comfort-height toilet | $606.06 | $18,863.61 |
The tile alternate is an allowance difference, 110 square feet at $7 more of your cost, marked up like the base. Fixr prints porcelain floor tile at $3 to $30 a square foot, so the base sits at the bottom of that range.
The toilet alternate is a material swap marked up like any other. It moves $400 of cost, the gap between the $200 and $600 ends of Fixr's toilet range.
Options win work. In ServiceTitan's 2025 survey of more than 1,000 residential contractors, run by Thrive Analytics, 54% of thriving shops offered three options on at least half their jobs. Struggling shops did it on fewer than 10%.
The cost-built price against what homeowners read
Here is the sample beside three homeowner guides, each written for people hiring a contractor.
| Source | What it covers | Price |
|---|---|---|
| This sample estimate | 5 x 8 full gut, Minneapolis | $18,257.55 |
| Thumbtack, July 2026 | 40 sq ft full bath | $9,809 to $18,640 |
| Thumbtack, July 2026 | 40 sq ft, average finishes | $11,338 to $17,433 |
| Fixr, January 2026 | 40 sq ft bathroom | $2,800 to $16,000 |
| This Old House, July 2026 | Small bath, 40 to 60 sq ft | $12,695 to $14,845 |
| This Old House, July 2026 | Full remodel, average | $18,706 |
The sample lands inside Thumbtack's full-bath range and under This Old House's full-remodel average. It sits $825 above Thumbtack's average-finish top and $2,258 above Fixr's top for 40 square feet.
That gap is what the scope block is for: a gut to the studs with licensed subs costs more than a refresh.
Homeowners price remodels hardest in March
We pulled 12 months of Google search data for 20 remodel cost, estimate and template searches on November 25, 2026. Pick a search in the tool below and switch to the month view to see its year.
The nine homeowner remodel cost searches added up to 95,200 in March and 48,500 in September, a 1.96 times swing. We computed that by adding Google's monthly counts for the nine. Bathroom searches were 56% of them across the year.
The five template searches by contractors also peaked in March. "Bathroom remodel estimate" drew the highest click price of all 20, at $59.85. Have your template ready before spring.
A remodel estimate and a commercial bid from plans are different jobs
A residential remodel is priced from a walkthrough. You measure the room and write the scope yourself, and allowances exist because the customer picks finishes after signing.
A commercial bid works from someone else's drawings and specifications. The work is the takeoff, measuring every quantity off the plans, and the owner or general contractor usually sets the bid form and the alternates. Our remodeling estimating software guide covers the takeoff tools for the jobs that arrive with drawings.
Estimate, quote, bid or proposal: one short answer
The words get used loosely. Housecall Pro defines the first three, and the fourth is ours.
- Estimate: "a rough calculation of the cost of a project." Housecall Pro adds that estimates typically are not binding.
- Quote: a specific price for a defined service.
- Proposal: a more detailed and comprehensive plan for the project.
- Bid: a price submitted against someone else's plans, often in competition.
Minnesota does not care about the label. Statute 326B.809 puts proposals, estimates, bids and quotations under the same rule as contracts for its licensees.

Each must be in writing with three things: a detailed summary of the work, the specific materials or standard features and the total price or how it will be calculated. All of it signed and dated by both sides.
Validity dates, deposits and change orders: what the states print
The template prints a 30-day validity date. After that, the subcontractor bids and material prices get rechecked before the customer signs.
Deposit rules come from the state, and they differ:
- Minnesota: the Attorney General's remodeling handbook says a "good faith" down payment is customary and should be a small percentage of the job.
- California: the Contractors State License Board caps a home improvement down payment at $1,000 or 10% of the price, whichever is less.
- Florida: statute 489.126 says a contractor paid more than 10% up front must apply for permits within 30 days and start within 90 days of the permits, unless there is just cause.
- Jobber's guide says deposits are usually 25% to 50% of the job, and warns that states limit them.

The California page also says payments cannot run ahead of the work performed, apart from the down payment. The sample's draws follow the work for that reason. In Minnesota, the Attorney General notes buyers get three days to cancel a sale made at their home.
The change-order sentence covers the rest. Anything added or found after work starts is written up and signed before work continues. Our change order template is the form for that step.
Free estimates, design fees and trip fees
FreshBooks' guide, updated April 2024, prints $150 to $1,000 for estimates that charge, and says estimates tend to be free for small, straightforward jobs. It also cites Remodelers Advantage: the fee can be deducted from the project price when the customer signs.
Count what free costs you. Five hours of walkthrough and pricing at the sample's $70 is $350 of cost on a job you may not win. Count those hours in your billable share.
Send it within a day and follow up on a schedule
No published study measures how sending speed changes approval on remodel estimates. Vendor advice points one way.
- Jobber's quoting guide says to send by email or text within 24 to 28 hours of the site visit.
- Housecall Pro recommends a first follow-up 24 to 48 hours after sending, a second 4 to 5 days later and a last one a week after that.
- In ServiceTitan's survey, 47% of contractors over $10 million in revenue said following up on estimates brings in 11% to 15% of their income.
Building construction estimates in software
A spreadsheet works for a one-crew shop. Software lets the customer tick alternates on a phone, sign and pay a deposit in one step.
Jobber's help center, updated March 10, 2026, says clients can select optional line items and the quote total adjusts automatically. A percentage deposit follows the items selected. The feature is on select plans.
Remodeling tools differ most in whether they ship with a cost database. Prices change often, so the remodeling estimating software comparison keeps every printed price in one place.
Is this estimate ready to send?
Run your next estimate through the checklist below, built from the template's sections.
Six mistakes that lose the job or the margin
- One lump-sum line. "Bathroom remodel, $18,258" invites a comparison the customer cannot make. The trade lines make it for them.
- Adding percentages to cost. A 34% markup on the sample leaves $216 of profit. Divide by 0.66 instead.
- Subs and allowances at cost. Overhead is a share of every revenue dollar, so a line with no markup is paid for out of your profit.
- Allowances with no due date. A vanity picked in week three stalls the plumber and the schedule.
- No exclusions. Whatever the estimate does not rule out, the customer assumes is in.
- No valid-until date. An estimate signed in May at November's sub bids comes out of your margin.
When the estimate is right and the phone is quiet
A good estimate converts the walkthroughs you get. It cannot create them.

The thing to copy is the button: put the price request in the header and again under the headline. Our remodeling leads guide ranks the channels that fill the calendar.
Skill Mammoth builds websites and runs marketing for contractors and home service businesses. Plans start at $350 a month, and a website build is $3,000 or $150 a month for 24 months. If you are just opening the doors, start with how to start a construction company.
The construction estimate workbook and PDF are free in the contractor templates pack. The contractor invoice template carries the signed estimate through to the bill.
Want more walkthroughs on the calendar?
We build the website and run the marketing that fills a remodeling schedule. Plans start at $350 a month.
Frequently asked questions
What should a construction estimate include?
Identity with license and insurance, an estimate number and valid-until date, both addresses, the scope by trade division, existing conditions, allowances, subcontractor lines, permit, dumpster and cleanup, schedule and draws, exclusions, alternates, then terms and a signature line. Minnesota's statute 326B.809 requires a detailed summary of the work, the materials and the total price on every estimate a licensee writes.
How do you price a construction estimate?
Add crew hours times the cost of a billable hour to what materials and subcontractors cost you, then divide by one minus your overhead and profit shares. At 24% overhead and 10% profit the divisor is 0.66. On the sample bathroom remodel, $11,720 of direct cost, allowances included, prices at $17,757.55, and the $500 permit passes through at cost for an $18,257.55 total.
How much should a general contractor mark up subcontractors?
We found no published figure for sub work alone, so set your own. The sample uses the same 51.5% markup as everything else, because NAHB counts trade contractor costs inside cost of sales and the overhead has to be paid from them. You can roll the markup into the sub's line or show the bid and a separate coordination line. The price is the same.
What is an allowance on a construction estimate?
A dollar amount held for an item the customer has not picked yet, such as a vanity or tile. Print the amount, a date the picks are due and how the difference is settled. The sample carries $1,500 for the vanity, $1,200 for the tub and valve trim and tile at $3 a square foot, all at cost, marked up like any material, with overages on a change order.
How long should a construction estimate be valid?
Jobber's quoting guide says most service businesses expire quotes after 30 days and suggests 14 to 21 days when material costs are volatile. The sample uses 30 days with a printed valid-until date. After it passes, recheck the subcontractor bids and material prices before the customer signs, because those are the lines that move.
How much deposit can a contractor ask for on a remodel?
It depends on the state. California caps a home improvement down payment at $1,000 or 10% of the price, whichever is less. Minnesota's Attorney General says a good faith down payment should be a small percentage of the job. In Florida, taking more than 10% starts a 30-day clock to apply for permits. The sample asks 10% at signing and ties the rest to finished stages.