TL;DR
- An electrical estimate needs one block most templates skip: panel and service details, circuits by count, wire by the foot, permit, utility steps and code notes.
- Price every line from a loaded hour. A median-wage electrician at an electrical contractor ($29.60, BLS) costs about $66 per billable hour, which bills at $113.79.
- The sample job, a 200-amp upgrade with an EV circuit in Saint Paul, totals $4,858.40 with the $116 permit passed through at cost.
- Minnesota's 2026 code adds an outdoor disconnect and a surge device to any service replacement, so a 100-amp swap prices at $2,808, above Fixr's $1,000 to $1,600.
- The Excel workbook with live totals and the print-ready PDF are free in our contractor templates pack.
- Skip the one-line "panel upgrade" estimate. It loses to the itemized one.
An electrical estimate template that wins the job has nine sections, and the one most free templates leave out is the panel and service block. Price each line from a loaded labor hour: a median-wage electrician costs about $66 per billable hour, which bills at about $114 once overhead and profit are in.
This guide is for the owner or office manager who writes estimates at a one-to-ten-truck electrical shop. It walks this electrician estimate template line by line and prices a sample job with the arithmetic shown. Every figure was read at its source on November 20, 2026.
Download this electrical estimate template. The editable Excel workbook with the totals wired up, a field guide tab, and a print-ready PDF are free in the contractor templates pack, alongside the other trades.
The electrical estimate template, section by section
| Section | What goes in it |
|---|---|
| 1. Identity and license | Name, phone, license number, insurance carriers |
| 2. Numbers and validity | Estimate number, date, days valid, proposed start |
| 3. Customer and service address | Both addresses, year the house was built |
| 4. Panel and service details | Amperage, brand, age, spaces free, meter location |
| 5. Circuits, devices, wire and conduit | Devices by count, wire and conduit by size and foot |
| 6. Options | Each tier and add-on priced as its own line |
| 7. Permit, inspection and utility | Who pulls it, the fee, the utility sequence |
| 8. Code notes | Sections the job triggers, from the adopted edition |
| 9. Price, terms and acceptance | Labor, materials, deposit, warranty, change orders, signature |
Sections 4, 7 and 8 make it electrical. Housecall Pro's free electrical template has no field for panel, amperage, permit or code, and Jobber's has none of the three either. Neither says how to price a line.
Walk the electrical estimate template top to bottom
Here is each section, filled in for a sample job: a 1958 house in Saint Paul with a full 100-amp panel, where the owners want a Level 2 EV charger.
Identity, license and validity
Print the business name, phone, state electrical license number and insurance carriers. Minnesota's Attorney General sends homeowners to the state's licensing office, so put the number where they look first.
Then the estimate number, the date, the proposed start and a validity line. The sample says 30 days, a choice the terms section explains.
Customer and service address
List both addresses even when they match, plus the year built. The permit and the utility work order key on the service address.
Panel and service details
This block sells the upgrade. Write the existing service, then the proposed one.
- Existing: 100A overhead service, indoor meter, a 20-space panel from about 1975, no spaces free, 18 circuits in use.
- Proposed: an outdoor meter-main, a meter socket and main breaker in one box, plus a new 40-space panel in the old basement spot.
- Feeder between them: 4/0 aluminum SER (service entrance) cable, the size Minnesota's inspection checklist lists for a 200-amp service.
Circuits, devices, wire and conduit
Count circuits and devices. Wire is the line customers question, so show sizes and feet.
- 18 existing circuits reconnected and labeled in a new directory.
- One new 50-amp, 240-volt circuit for the charger, in 6/3 NM-B (plastic-sheathed) copper cable, 45 feet.
- 3/4-inch EMT (thin steel) conduit, 10 feet, where the cable crosses the garage wall.
- Grounding: 30 feet of #4 copper and two ground rods.
Options priced as separate lines
The service sells in three sizes, so the estimate prints three lines: 100, 150 and 200 amps. In the workbook, put 1 in the qty of the option the customer picks and leave the others blank. Every price shows, and only the pick reaches the total.
Add-ons work the same way. The sample customer declined both, GFCI (ground-fault) receptacles and a load calculation.
Permit, inspection and utility
Say who pulls the permit, what it costs and how the fee is built. Saint Paul charges $85 for a service permit, which covers every reconnected circuit, plus $15 for each added circuit or feeder and a state surcharge of at least $1.
The sample counts the new feeder and the EV circuit, for $116. Confirm how the office counts yours. Where the state inspects, the same job runs about $120 under the fee schedule in Minnesota Statutes 326B.37.
Then the utility sequence. Xcel Energy's 2019 upgrade sheet says it sets a meter on an altered service only after the local inspector releases it, and the customer buys the socket, rated 200 or 320 amps with a lever bypass.
Code notes from the adopted edition
Minnesota enforces the 2026 National Electrical Code (NEC) for permits filed from August 17, 2026. The state's inspection checklist names what a service replacement brings with it:
- An outdoor service disconnect within 50 feet and visible from the house (230.70).
- A Type 1 or Type 2 surge protective device rated at least 10kA (230.67).
- A grounding electrode system, with a rod supplemented unless it tests at 25 ohms or less (250.50, 250.53).
AFCI (arc-fault) protection comes in only where a branch circuit is modified, replaced or extended (210.12).
Saint Paul's service-upgrade sheet, dated July 2023, already applied the outdoor disconnect to same-amperage swaps. Print the section numbers, because they explain the price before the customer asks.
Labor and material lines
Labor is hours times your billed rate, and materials are supplier cost through the same divisor. The next section builds both. The sample's wire, conduit, breaker, rod and fitting prices and the Option A and B hours are our placeholders. Use yours.
Terms and the signature line
Deposit and balance, warranty, the change-order sentence, then the option picked, signature and date. The sample asks 10% at signing, $485.84, and the balance when the inspection passes.
The sample lines:
| Line | Qty | Unit | Rate | Amount |
|---|---|---|---|---|
| Option A: 100A panel, keep 100A service | job | $2,807.50 | Not picked | |
| Option B: 150A service upgrade | job | $3,506.69 | Not picked | |
| Option C: 200A service upgrade | 1 | job | $3,671.18 | $3,671.18 |
| EV circuit labor | 4 | hr | $113.79 | $455.16 |
| Cable, 6/3 NM-B copper | 45 | ft | $7.33 | $329.85 |
| Conduit, 3/4 in EMT | 10 | ft | $1.76 | $17.60 |
| Breaker, 50A 2-pole | 1 | each | $41.03 | $41.03 |
| Utility coordination, inspection visit | 2 | hr | $113.79 | $227.58 |
| Saint Paul permit, at cost | 1 | each | $116.00 | $116.00 |
| Add-on: EV load calculation, Option A only | each | $113.79 | Declined | |
| Add-on: GFCI receptacle, basement | each | $92.07 | Declined | |
| Subtotal | Picked lines only | $4,858.40 | ||
| Sales tax | 0%, inside material prices | $0.00 | ||
| Estimate total | Option C with the EV circuit | $4,858.40 | ||
The tax line is zero on purpose. Minnesota's Department of Revenue tells contractors to pay tax on materials and not to charge it on construction contracts. Check your state before copying that.
Price each line from a $66 loaded hour
This is how to write an electrical estimate that holds its margin. The Bureau of Labor Statistics (BLS) supplies the first two steps.
| Step | Figure | Source |
|---|---|---|
| Median wage at electrical contractors | $61,570 a year, $29.60 an hour | BLS, May 2025 |
| Times benefits and required taxes | 1.45 | BLS employer costs, June 2026 |
| Loaded hour | $42.92 | Our arithmetic |
| Divided by the billable share | 0.65 | Field Promax, 300 HVAC firms |
| Cost of a billable hour | About $66 | Our arithmetic |
| Divided by what overhead and profit leave | 0.58 | 27% overhead, 15% profit |
| Billed rate | $113.79 an hour | |
The 1.45 is from the BLS employer cost survey: construction, extraction, farming, fishing and forestry workers earned $32.17 an hour in June 2026, and employers paid $14.47 more in benefits and taxes.
The billable share is the weak link. A billable hour is one a customer pays for. Field Promax measured 5.7 billed hours in an 8.8-hour paid day across 300 HVAC companies, as ACHR News reported in June.
Nobody measures it for electricians. ServiceTitan's electrical guide calls 70% to 80% average and names no sample. Pull four weeks of timesheets and use your own.
Overhead and profit set the divisor
Overhead is every cost not tied to one job. Tax returns give the firmest figure. The vendor guides name no sample.
- IRS Statistics of Income, tax year 2023: electrical contractor corporations kept 34.1% gross and 6.6% net, leaving 27.5% for overhead.
- ServiceTitan, July 2026: 20% to 30% of revenue for an average shop.
- Housecall Pro, October 2026: roughly 13% to 20% of sales.
- Profit: Jobber's April 2026 guide calls 12% to 18% healthy and suggests 15% to start.
We use 27% overhead and a 15% profit goal, which leaves 0.58 of each dollar. Use the overhead number from your own profit and loss statement.
Our labor rate calculator reaches the same $66 billable hour. It bills near $110 because it uses 30% overhead and a 10% profit.
For comparison, Fixr tells homeowners electricians charge $40 to $120 an hour. The bottom of that range is less than the $42.92 loaded hour, before any unbilled time.
The arithmetic for the 200-amp line
Option C is 16 hours of labor, the top of Fixr's four to eight hours with two electricians, or $1,820.64. Materials go through the same divisor, a 72% markup on cost.
| Option C material | Your cost | Billed at cost / 0.58 |
|---|---|---|
| Meter-main, 200A, outdoor | $306.11 | $527.78 |
| Panel, 200A, 40-space | $300.00 | $517.24 |
| Surge protective device, Type 1 | $185.00 | $318.97 |
| SER, grounding, rods, fittings (placeholders) | $282.20 | $486.55 |
| Materials | $1,073.31 | $1,850.54 |
Labor plus materials makes Option C $3,671.18. The meter-main and surge device costs are Standard Electric Supply's web prices for Square D parts. The panel is the low end of Fixr's $300 to $400 for a 200-amp box.
Housecall Pro's guide says materials markups average 2 to 6 times cost. The divisor's 72% sits under that, which suits a meter-main. Small parts can carry a steeper tier.
Set your own numbers in the calculator below. Its default is the template's sample job, and the four buttons load it plus three common jobs with published hours.
The calculator's default prices at $4,742, which is the template's $4,858.40 subtotal less the $116 permit the template passes through at cost.
Adding 42% to cost as a markup quotes the sample job at $3,906 and nets $101 instead of $711. Our markup vs margin guide has the conversion table.
Price the 100, 150 and 200 amp tiers as three lines
Here are the three service options beside what two cost guides tell homeowners. Fixr updated its page in January 2025 and This Old House in March 2026.
| Option | Cost-built price | Fixr tells homeowners | This Old House tells homeowners |
|---|---|---|---|
| A: 100A panel, same service | $2,807.50 | $1,000 to $1,600 | $800 to $1,500 |
| B: 150A upgrade | $3,506.69 | $1,500 to $2,800 | Not listed |
| C: 200A upgrade | $3,671.18 | $1,800 to $4,500 | $1,300 to $3,000 |
The 200-amp line sits inside Fixr's range. The 100-amp line sits above both guides, and the code explains why.
of the 100-amp option's price is the outdoor disconnect and surge device Minnesota's 2026 code adds to a service replacement, at the sample's supplier prices. Without them the line would be $2,013.06.
We got that from the template: a Square D outdoor 100-amp breaker box bills at $475.47 and the surge device at $318.97. Neither cost guide prices either item. A customer holding Fixr's page will read your swap as $1,208 high unless the code notes sit beside it.
The gap between Options B and C is only $164.49. The labor, the surge device and the grounding are the same, and Xcel only accepts a meter socket rated 200 or 320 amps. Only the panel and the cable get cheaper. Print the gap, because it makes the 200 an easy pick.
The EV charger with or without the upgrade
The EV circuit prices the same on either panel: $843.64 in the sample. Keeping the 100-amp service adds one line, a $113.79 load calculation to show whether the charger fits.
EnergySage's June 2026 page tells homeowners a service upgrade adds $1,500 to $4,000 or more on top of the charger.
Options pay. In ServiceTitan's 2025 survey of more than 1,000 residential contractors, run by Thrive Analytics, 54% of thriving shops offered three options on at least half their jobs. Struggling shops did it on fewer than 10%.
Estimates priced right, but not enough of them?
Skill Mammoth builds websites and runs marketing for electricians and other home service businesses. Free 10-minute audit of your current site.
A service-call estimate and a bid from plans are different jobs
A service-call estimate is written on site after one visit, and the template above is built for it. Flat prices per task work best here, and our guide to electrician flat rate pricing covers that book.
A bid from plans prices new construction or a commercial fit-out from drawings. The work is the takeoff: counting every device and measuring every run off the plans. The general contractor usually sets the bid form.
Estimate, quote, bid or proposal: what you are promising
The words get swapped, and the difference matters when a customer holds you to a number. Housecall Pro defines the first three. The fourth is ours.
- Estimate: a rough calculation of cost, typically not binding.
- Quote: a specific price for a defined service.
- Proposal: a more detailed, comprehensive plan for the project.
- Bid: the price you submit to win a competitive job, usually against plans and a bid form.
A fixed price with a validity date is a quote by those definitions, whatever the title says. The same workbook serves as an electrical quote template or an electrical bid template with a new title line.
Validity, deposits and change orders: what the states print
Validity has no state rule we found. Housecall Pro's template example says 7 days. We picked 30: long enough to decide, short enough that supplier prices still hold.
Deposits and cancellations do have rules in some states.
- Minnesota: the Attorney General says the law requires contracts and change orders in writing, and that a down payment should be a small percentage of the job.
- Minnesota: the Home Solicitation Sales Act gives a buyer three business days to cancel a sale made at home.
- California: the contractors board caps a home improvement down payment at $1,000 or 10% of the price, whichever is less. Jobs over $500 need a contract.
- Federal: the FTC's Cooling-Off Rule covers home sales of $25 or more, with a cancellation form, and exempts emergencies and repairs the customer asked for.
Print the cancellation notice when you sign at the kitchen table, and put every mid-job addition on a signed change order.
Free estimates, trip fees and the diagnostic visit
Housecall Pro's template page says diagnostic fees are standard and free estimates are common for new installations.
An install estimate is a sales call for a job worth thousands, so it can be free. A repair visit is the job, so charge a diagnostic fee and credit it if the customer books. Our electrician invoice template shows that credit as its own line.
A free one-hour visit still costs $66 in labor. Count those visits in your billable share, or the rate drifts low.
Send it the same day and follow up twice
We found no published figure on how fast an estimate should go out. The follow-up has numbers. In the same ServiceTitan survey, 47% of contractors over $10 million in revenue said following up on estimates brings in 11% to 15% of their income.
Jobber's Connect plan and up send two automated quote follow-ups, set up to 90 days out. Housecall Pro can stamp a default expiration date on every estimate.
Homeowners price panel work in every month
We pulled 12 months of Google search data for the cost searches that come before an electrician's visit. Pick one below and switch to the month view.
Panel and service searches barely move. The five in that group summed to 9,940 in February and 12,260 in March, a 1.23 times swing, from adding Google's monthly counts across the year.
Devices swing hard. The five device and wiring searches ran 3.2 times higher in March than in October. EV charger searches peaked in March and May and bottomed in August.
That is flatter than the 6.7 times swing our HVAC pricing guide found in air conditioning searches. Panel estimates get written all year against a cost guide the customer read that week.
Build it in software once the template works
A spreadsheet is fine for a few estimates a week. Past that, software saves the retyping, with a price book, online options and the estimate turning into an invoice.
Our electrical estimating software guide compares every tool that prints a price, from quoting apps to takeoff suites.
Six mistakes that lose the job or the margin
- One line for the whole job. "Panel upgrade, $3,200" loses to the itemized estimate and invites a dispute about what was included.
- Leaving out the code items, about $790 the customer will not see coming.
- Pricing from Fixr's $40 to $120 an hour, whose bottom is under a median electrician's loaded cost.
- Adding overhead and profit to cost as a markup, which cuts the sample job's profit from $711 to $101.
- One option, when thriving shops show three far more often.
- No follow-up, when nearly half of $10 million shops credit it with 11% to 15% of income.
Run your next estimate through the check below before it goes out.
When the estimates are right and the phone is quiet
A good estimate wins more of the jobs you price. It cannot create the requests. Our guide on how to get more electrician leads ranks the channels by what a booked job costs.
Skill Mammoth builds websites and runs marketing for contractors and home service businesses. Plans start at $350 a month, and a website build is $3,000 or $150 a month for 24 months. If your estimates win and the calendar still has gaps, that is the part we can help with.
The workbook and the PDF version of this template are in the free contractor templates pack.
Want more estimate requests at the prices you just set?
We build the website and run the marketing that fills an electrical schedule. Plans start at $350 a month.
Frequently asked questions
What should an electrical estimate include?
Nine sections: identity and license, an estimate number with a validity date, the customer and service address, panel and service details, circuits and devices by count with wire by the foot, options as separate lines, permit and utility steps, code notes and the price with terms and a signature line. The panel, permit and code blocks are what free templates usually leave out.
How do you price an electrical estimate?
Multiply labor hours by your billed rate, and divide material costs by the share of each dollar left after overhead and profit. At a $66 cost per billable hour, 27% overhead and a 15% profit goal, that share is 0.58. Labor then bills at $113.79 an hour and materials carry a 72% markup. The sample 200-amp upgrade prices at $3,671.18.
How much should an electrician charge per hour?
Enough to cover a billable hour plus overhead and profit. At the BLS median wage at electrical contractors, $29.60, with 45% added for benefits and taxes and 65% of paid time billed, an hour costs about $66. At 27% overhead and 15% profit it bills at about $114. Fixr tells homeowners electricians charge $40 to $120, and $40 is below the loaded wage alone.
Should electricians charge for estimates?
Housecall Pro's template page says diagnostic fees are standard on repair calls and free estimates are common for new installations. A practical split is free estimates for installs and upgrades, and a trip or diagnostic fee for repairs that is credited if the customer books the work. Count the free visits when you set your billable share, since each one is an unpaid hour.
How long should an electrical estimate be valid?
No state rule we found sets a period. Housecall Pro's template example uses 7 days, and its software accepts any number. The sample template uses 30 days, which gives a homeowner time to decide while the supplier prices behind each line still hold. Print the date on the estimate and follow up before it passes.
What deposit can an electrician ask for?
It depends on the state. California caps a home improvement down payment at $1,000 or 10% of the price, whichever is less. Minnesota's Attorney General says a down payment should be a small percentage of the job. The sample template asks 10% at signing, $485.84, with the balance due when the city inspection passes.